FOTP trail crew volunteers, were last seen entering Bigfoot territory on the Crowe Gulch trail on the morning of August 26, 2023. The mission: clear corridor on this trail and the Mt. Esther trail in preparation for the Bigfoot Benefit hike last fall … as Denise, Carol, and Doug entered the mist they encountered bigfoot … they haven’t been seen since, or have they?
Barr Trail
August 2023 News Letter – Fenceline Repairs
Well, that tumbling boulder sure gave us a lot of things to fix on Barr trail. Here are some pictures of what we were doing on our first four days of fence repair, May 20 and 25, and June 8 and 11.
May 20: Our first job was to make a good path around the boulder. Here’s me sawing through the mangled trunk of the tree that finally stopped the boulder.
We’ve talked about “the boulder” that tumbled down the hillside and crashed through the fence in multiple places. But there was more than one boulder tumbling down the hill, although we don’t really know how many. It’s clear this smaller (about 4’x2’x3’) boulder (to the left of the trail in the next picture) was a new arrival. We’re glad it stopped where it did. And we decided to leave it right where it is, and build the new fence around it.
On May 25 we were back on Barr trail, doing routine (not boulder damage) post and rail work Here’s Mike installing a new fence rail in a scenic location.
Then we needed to do some quick repairs on the tread on the trail segment above the boulder. Here Susan argues with Brian while I take pictures and Courteney does all the work
On June 8 we were back to repairing fence damaged by the boulder above SB9. Here’s Shanda getting ready to drill the holes in the post so she can attach the rails.
Finally, on June 11 we built a drain structure on the trail before we replaced the segment of fence that now goes over it. Since the big boulder followed the existing drainage channel, we decided it would be a good place to enhance and armor the drain. The drawing on the picture explains what we want it to do. And so far, it’s doing its job very well.
So that’s what we got done by June 11. But wait, there’s more!
We’ve done much more than this. Stay tuned, I’ll get another newsletter out as soon as I can. Better yet, there are still a few more workdays on the schedule this season. Join us and see for yourself!
Sign up at https://friendsofthepeak.org/sign-up/
– Steve Driska
2023 Trail Work Season Recap Part 1
Our 2023 fieldwork season was scheduled to start on Thursday May 11. A group of Walmart managers were attending a meeting in the area and had volunteered to help us on Barr trail. They were registered, parking was arranged, and we looked to be off to a great start.
But there was lightning, thunder and over 3” of rain on this date. and Brian had to cancel the workday because of safety issues. It was the right call, and that was confirmed when we learned about the tumbling boulders. On our May 20 workday we assessed the damage.
In the picture above, Brian is standing next to largest of the boulders so you can get a sense of its size. It tumbled down the hillside, demolishing fences on three segments of the trail, and came to rest in the middle of the trail below switchback 9 (at 38° 51′ 18.438″ N, 104° 56′ 21.228″ W, which is about 0.9 miles up from the trailhead)
We sawed through the crushed and mangled tree trunk, removed it, and made a smooth and level path around the boulder on the uphill side. The path is narrow but passable.
Further up the trail, Susan and Brian survey the damage to the fence on the trail segment directly above the boulder
And the segment above this took a beating too. The picture above is above switchback 10 at milepost 1.0. Some of these rails (the lighter colored ones) were just replaced in 2022
The map below shows what happened. The boulder moved 243′ vertically and 390′ horizontally. The stars show where it broke through the fencing, and the yellow boxes mark the switchback numbering system we use, starting from the trailhead.
So…… in addition to the usual maintenance work on Barr trail, we’ve had a lot more to do.
Stay tuned and we’ll update you on the progress we’ve made so far. Better yet, come see it for yourself- sign up for our Barr trail post and rail workdays at https://friendsofthepeak.org/sign-up/
Friends of the Peak Newsletter: March 2023
Hello Friends,
We hope 2023 is off to a good start for you and that you’ve enjoyed the great outdoors
this winter. It’s time for another Friends of the Peak newsletter highlighting what we did in 2022.
At the beginning of 2022, we added three new board members, Vickie Laughlin, Russell Iverson, and Steve Driska. Brian Van Valkenburg scheduled an entire season of work for 2022. In addition to our usual projects, our friends from the Pikes Peak Group of the Colorado Mountain Club, led by Tom Mowle, asked us to partner with them to re-route a segment of the trail to Horsethief Park. This was to prevent the closure of the trail by the Forest Service because of a land dispute; a recent survey showed the trail crossed private property. You probably heard about this land dispute because it was well publicized in the media. This trail starts at Highway 67 and allows access to many popular destinations, including Horsethief Falls, Pancake Rocks, and Sentinel Point. This became a high-priority project for us.
Before the 2022 season even started, board members were doing scout hikes on trails where we planned work, specifically on the North Catamount section of the Ring the Peak Trail and of course, on Barr trail. Our volunteers were also helping plan the Horsethief Park re-route project.
We started the season on a hot and dry Thursday in mid-May doing tread and drain work on Barr trail as multiple grass fires broke out in the city below. Nine days later, our first scheduled Post and Rail workday on Barr had to be canceled by a foot of snow on the trail. Colorado weather- you gotta love it!
In early June, we worked on the Catamount segment of the Ring the Peak trail. This beautiful trail continues the dirt road along the north shore of North Catamount Reservoir towards Raspberry Mountain and the Mennonite camp off Highway 67. We worked on about a mile of trail that hadn’t been touched for several years but was still in good shape. At its western end, we removed many small evergreens and shrubs taking over the trail. Further east (picture), we relocated about 100’ of trail upslope a few yards to avoid a deep eroded incision in the road caused by water draining to the adjacent North Catamount Creek.
June 21 was Pikes Peak United Way’s Day of Action. A great crew of community volunteers from United Way joined us to work on the Seven Bridges Trail. Thank you to these amazing volunteers who gave their time and energy moving rocks, hauling timbers, and digging in the dirt.
Saturday and Sunday, June 18 and 19, were the first two days of the Horsethief Park trail reroute with the Colorado Mountain Club. The new trail was about 550’ long, requiring extensive removal of small trees in the tread and a significant amount of rock wall construction. The trail had been staked and flagged, and sawyers had previously cut trees in the tread, leaving about three feet of trunk to use as leverage as we dug out the roots. About 45 volunteers worked on the first day and 25 on the second.
How the trail looked when we finished up on the first day
Here’s Dan working on the rock wall and ramp to connect the new trail to the old trail uphill from
the segment on private property.
And yes, all those rocks Dan is standing on were installed that weekend. After that first weekend of work, the forest service was satisfied that the trail was a functional reroute. This meant that they would not have close the old trail. Success! But both FotP and CMC have very high standards, so several volunteers from both organizations returned later to do finishing touches on the trail.
Back to Barr Trail:
We knew from our scout hikes that extensive work was needed on the fences along Barr trail. We had four workdays repairing fences on Barr Trail (“post and rail days”). As anyone who has hiked on Barr trail knows, trying to repair the fences is a never-ending task. Most problems are caused by age, weather, and falling trees, but some are caused by hikers taking shortcuts through or over the fences.
Here’s a “before” picture of fence damage at the end of winter, above switchback 10, about a
mile up from the trailhead. A tree had fallen on the rails to the left, breaking them and splitting
the post. Surprisingly, the post was still usable. As shown in the following picture, we replaced the two broken rails in July.
Our final Post & Rail Day on Barr was in August. These volunteers worked through a light rain on a
pleasantly cool and foggy day. Despite the weather, they’re all smiling.
This year we also spent a few days on the Saint Mary’s Falls and Seven Bridges trails, two of our favorites. On one of our work days on the Seven Bridges trail, we worked to protect the trail from further erosion towards the creek.
Brian, Mike, Dan, and Denise are setting stones in one of two drains we greatly expanded and armored to better handle water draining across the trail from the steep hillside on the right.
This year the Pikes Peak Ascent and Marathon moved to a new weekend later in the year. This meant our three traditional workdays to remove slip and trip hazards just before race weekend was held in September. On the first day, we started from the trailhead and worked on the bottom of the trail, ending at switchback 18 (the “corral” in trail worker slang, about 1.75 miles from the trailhead). Our relationship with PPAM is excellent; the organizers (and racers) appreciate our efforts to make the course safer. In return, on two of the workdays, PPAM gave us a ride up Longs Ranch Road with marathon staff who were hauling water tanks up for the aid stations. (Anytime you can get a ride and not have to carry tools up 2,000’ vertical feet, it’s a real treat!) This allowed us to start work at No Name Creek near milepost 3.0 and work uphill to milepost 3.5 and then down to the junction with the Incline return trail (near milepost 2.5) on one of the days. We finished tuning up the trail from the Incline return trail down to switchback 18 on the final workday.
Some of our friends from the AdAmAn club joined us on a cool and rainy Saturday for this work, and on the following Thursday, a group of volunteers from Cisco joined us. Both groups were great and fun to get to know and work with.
Our AdAmAn friends at PPAM headquarters before they got wet.
Breaking up into work teams and dividing the tools at No Name Creek. The rain didn’t hamper our work, and many of us enjoyed seeing these familiar places in different weather. (At least I did.) Our volunteers from Cisco had nicer weather the following Thursday.
Here are some of the Cisco folks and some of our “usual suspects” at the tool talk.
Besides removing slip and trip hazards, we cut back scrub oak and mountain mahogany encroaching on the trail (i.e., corridor clearing). Whenever possible, we cleaned out drains.
Here are two of the Cisco volunteers rejuvenating an existing drain near milepost 2.0:
Finally, we had something new:
The Second Annual Pikes Peak Bigfoot Hunt to benefit Friends of the Peak! Russ Iverson organized, publicized (even appearing on local TV!), and starred in this production as Bigfoot himself. The hunt was on the Mt. Esther/Crowe Gulch trail along the Pikes Peak Highway on a beautiful Saturday in late September. Those who bought tickets to be Bigfoot hunters and successfully found him were eligible for neat outdoor gifts.
Here are some happy prize winners getting their gifts from Russ at the night’s after-party. Like Clark Kent and Superman, you never see Russ and Bigfoot together.
So, to summarize, it was great to be back outside again, working on the trails we all love! The next newsletter will cover the end-of-season banquet, our post-season trail work on Barr, our involvement with the Manitou High School project, and pictures of our annual tool cleaning (Spoiler Alert: sparks will be flying).